The Challenge: Managing a Diverse Range of Parts and Handling Methods
A supplier of undercarriage components used in the manufacturing of heavy construction equipment lacked an inconsistent process for preparing finished products for shipment. Due to a diverse product line, loads varied throughout the day, requiring workers to use different handling methods.
The variability created several challenges:
- Diverse Components: Parts varied in shape and weight, making it difficult to establish a single handling method for every product.
- Inconsistent Handling: Workers needed to adjust how materials were lifted and moved throughout the day based on the specific component.
- Physical Strain: Repetitive lifting and positioning movements had the potential to place strain on workers' shoulders, necks, and backs.
- Shipment Preparation: Components needed to be accurately positioned in transportation racks for final preparation before shipment to OEMs.
Our customer needed a more consistent procedure that could accommodate the majority of its components while making the shipment preparing process more efficient and less physically demanding.
The Solution: A Free Standing Jib Crane with Flexible Load Handling
To simplify the material handling process, the company implemented a Gorbel® Free Standing I-Beam Jib Crane along with specially designed holders for transporting components.
The system provided the flexibility needed to handle the facility’s varied product mix:
- Capacity: One-ton lifting capacity to support component handling requirements.
- Flexible Positioning: The jib crane enables workers to position an electric chain hoist directly above the component being lifted.
- Adaptable Rigging: Depending on the component, workers can attach the hoist directly to the load or use a chain or synthetic sling.
- Specialized Handling: Specially designed holders help accommodate components for transport and shipment preparation.
Rather than rely on multiple handling approaches, the jib crane became the foundation of a more consistent process for lifting and positioning most of the company’s finished components.
The Execution: A More Consistent Handling Process
Workers use the Free Standing Jib Crane to position the electric chain hoist directly above each component before lifting. Depending on the part, the load is either connected directly to the hoist or lifted using a chain or synthetic sling.
Once secured, the component can be lifted and positioned into the appropriate transportation rack for final preparation before shipment to the OEM.
This approach gives workers a consistent handling procedure while retaining the flexibility required for a diverse product line. Using the jib crane to lift and position components also reduces the need for workers to perform repetitive movements that can place stress on the shoulders, neck, and back.
The Result:More Efficient Shipment Preparation
The combination of the Gorbel Free Standing I-Beam Jib Crane and specialized handling equipment established a more consistent process for preparing finished components for shipment:
- Improved Efficiency: Workers can more efficiently prepare components for shipment using a standardized handling process.
- Greater Flexibility: Direct hoist attachment, chains, and synthetic slings allow the system to accommodate components with varying shapes and weights.
- Reduced Physical Strain: Mechanical lifting and positioning reduce movements that can place stress on workers' shoulders, necks, and backs.
- Consistent Workflow: The jib crane provides a common handling method for the majority of components despite the company's diverse product line.
- Simplified Shipment Preparation: Components can be lifted and positioned directly into transportation racks used for final preparation before shipment to OEMs.